Do the battery terminal disconnection procedure.
Remove the drive belt.
Remove the intake manifold.
Disconnect the alternator connector (A) and the positive alternator cable (B), then remove the harness clamp (C) from the alternator.
Remove the alternator.
Secondary Shaft 2nd Gear Axial Clearance Inspection (A/T)
Install the thrust needle bearing (A), the needle bearing (B), 2nd gear
(C), the thrust needle bearing (D), the 43 x 54.5 mm thrust washer (E), the
39 mm cotters (F), and the cotter retain ...
Brake System Indicator
Brake System Indicator (Red)
The brake system indicator (red) normally comes on when you turn the ignition
switch to the ON (II) position, and as a reminder to check the parking brake. It
will ...
Change Lever Clearance Inspection (M/T)
Measure the clearance between the change lever (A) and the select lever
(B) with a feeler gauge (C). If the clearance is more than the service
limit, go to step 2.
...